Bray Solutions Pty Limited
Year
Service
Features of Plant
Inlet Flow & Pressure
Role in Project

1997
Goaf
*Fixed plant
*Three liquid-ring vacuum pumps *75kW electric motors/V belt drives
*Manual flow control by recirculation

1,500 actual litre/s

-50 kPa gauge
*Devised process concept
*Sized and specified equipment
*Wrote Functional Specification
*Led design review/HAZOP
*Oversaw mechanical commissioning







1999
Goaf
*Upgraded goaf plant for four vacuum pumps
*Redesign of separators
*Addition of inlet dropout box
*Rework of pipework
2,000 actual litre/s

-50 kPa gauge
*Retained existing process
*Carried out calculations
*Engineered separators, pipework, etc. for detailing by others
1998
Flare
*Vertical stack flare
*Methane from existing goaf plant
*Reduce greenhouse gas emissions under Shell Coal policy
1,100 litre/s
*Devised process concept to modify/connect to goaf plant
*Sized and specified equipment and stack, for detailing by others
1998
In-seam
*Movable plant
*Centrifugal fan
*55kW electric motor/VVVF drive
*Automatic flow control by variable speed
2,000 actual litre/s

-12 kPa gauge
*Devised process concept
*Sized and specified equipment
*Wrote Functional Specification
*Led design review/HAZOP
*Led design team
*Oversaw mechanical commissioning



Central Colliery Gas Plants and Flare